How I've run major projects — Ben Kuhn

Ben Kuhn's playbook for running large, high-stakes projects at Anthropic, distilled from "crisis project management" work. Key claim: excellent project management is extremely high-leverage and rarer than it needs to be — mostly because people lack a good playbook. The work mostly felt straightforward to him, but others consistently miss the moves.

Focus

Clear your schedule. Make the project the top idea in your mind (Paul Graham's phrase). Without this, projects go on autopilot — you keep them running but stop proactively thinking about non-obvious things (scope resets, priority changes, when to sound alarms). Crisis mode: 6+ hours/day. Non-crisis: still carve out dedicated daily time.

Plan for victory

Maintain a detailed plan for victory: a concrete list of steps that ends with the goal achieved. Its purpose is not optimism — it is an early-warning system. The most common megaproject failure mode is not freaking out soon enough; a concrete plan makes slippage visible early.

Two lessons from a real model-release sprint:

  • The plan made it clear 3 months out that things were tight → they pulled in help from another team
  • They underestimated several components, didn't check against the plan frequently enough, and still got crunched

Protective moves: add honest "slop" to estimates (most teams are too cowardly here); check against the plan frequently; sound alarms early when you go off-plan.

Run a fast OODA loop

OODA = Observe, Orient, Decide, Act. Most large projects are bottlenecked on information processing, not writing code. Getting complete information often IS the hard part. A recent training run example: the entire critical path was information round-trips between Anthropic and a compute partner — each step constrained by how fast info could flow.

Tactics:

  • Spend real time on it: running OODA loops is a primary time use, not a background activity
  • Communicate uncomfortably much: multiple daily calls in high-stakes phases; constantly bounce between groups
  • Track and prioritize biggest open questions: maintain a ranked living doc of top uncertainties; resolving them becomes the priority list; parallelize across people
  • Step back and reorient frequently: review priorities multiple times a day; parallelizing top items reduces switching costs when you do reprioritize

Overcommunicate

Everyone needs ambient awareness of (1) what else is going on, and (2) how their work fits the overall goal — so they can make good local decisions without a round-trip through you. Getting there requires repeating the same things far more than you expect. Synchronous meetings create common knowledge that async doesn't.

Break off subprojects

Past ~10 people, delegate project management (not just execution). Ideal delegation unit: crisp, simple, high-level goal with limited overlap with other workstreams. Bad: a 10-step checklist. Good: "get X working at Y throughput over Z protocol."

The best project managers are often not the strongest technical ICs — the key traits are organization and laser focus on end goals.

"Direction is more important than magnitude — it's usually better to have a lower-velocity project working on the right things than a higher-velocity one pointed at the wrong goal."

Keeping goals simple ≠ doing less. Find the latent structure that enables clean recursive decomposition — requires work to identify the right intermediate goals, but pays off immensely.

DRI starter kit (appendix)

DRI = Directly Responsible Individual. Lightweight system for new project leads:

  • Landing page / working doc: go/ link, concrete top-level goal, staffing, roadmap, important open questions list
  • Weekly 30-min meeting: backstop for coordination; creates common knowledge; 5m DRI review → 10m silent write → 10m sync discussion
  • Stack-ranked task list: people must understand priorities; kanban if there's a large backlog
  • Slack norms: no DMs (makes info undiscoverable); no centithreads (≥10 messages → short Tuple); bias toward fewer, larger channels
  • Weekly broadcast updates: signal-to-noise focused; "we accomplished Y" not "we worked on X"; state things crisply ("X improves eval Y by Z points")
  • Retrospectives: every 2-4 weeks; "what went well / what we could improve" format